Cost function for ion exchange
The original cost function (A1) is as follows:
This function has as a variable (x) that represents the pumping capacity in gpm (gallons per minute) which will be the same as the plant. The conversion of units (to L / s) is carried out:
Additional modifications to this function correspond to the correction of costs per year, with the CCI ENR index of 9547 of the year 2013, to obtain A3. Then part B2 related to the elasticity index is added. This is done in the same way as explained in the Cost Functions Wiki — General.
With the above, the following is the function obtained:
Share
Bibliography
-
Preliminary Cost Estimation Models for Construction, Operation, and Maintenance of Water Treatment Plants
Jwala R. Sharma, Ph.D., M.ASCE; Mohammad Najafi, Ph.D., P.E., F.ASCE; and Syed R. Qasim, Ph.D., P.E., M.ASCE
2013
Reliable cost estimation of construction, operation, and maintenance (O&M) of water treatment plants is essential for project planning and design. The authors have developed construction and O&M cost models for different unit operations and processes involved in water treatment plants. This paper presents the use of a single cost index to further update construction and O&M costs.
References
- ¿Qué es el Intercambio Iónico? https://cutt.ly/yTDXTU0